Connect with us

Aviation

Rehabilitation work on Abuja airport runway in progress – Official

Published

on

Rehabilitation work on Abuja airport runway in progress – Official

Julius Berger Plc, the contractor handling the rehabilitation work of the Nnamdi Azikiwe International Airport, Abuja, runway has commenced work, an official said on Wednesday.

Newsverge correspondent, who visited the airport reports that both workers and equipment have been fully deployed on the runway with major work underway.

Newsverge also observed that a substantial part of the runway has been excavated, showing that work has been on for a number of days already.

Mr Nuhu Mustapha, Deputy General Manager/Head of Department, Civil Engineering, Nnamdi Azikiwe International Airport, Abuja, told Newsverge that the work commenced on Thursday as soon as the airport was shut.

Mustapha said the contractor had shown that it would complete the work as planned, adding that work had commenced as scheduled, since the contractor had been mobilised.

He explained that the runway, which had a total length of 3.6 kilometers had been divided into three parts by Julius Berger with the plan to complete each of the one third in two weeks each.

According to him, the mailing (digging) of the first 1,200 metres has been done within one week, later on the asphalts will be laid and then the electric light fitting will be fixed.

“The length of the runway is 3.6 kilometres but so far, we have mailed one third of it, which is 1,200 metres and they are going to finish the mailing of this part today.

“We will work on that one third, mail it, put asphalt and the electrical fittings then move on to the second and third part.

“They have done the scan part of the mailing and the contractor said they are going to finish it as scheduled,” he said.

Mustapha also disclosed that the major work would be carried out on the middle portion of the runway which is 20 metres of the total 45 meters width of the runway.

He explained that the middle portion would be mailed (cut) by an average 17 centimeters deeper underground to address the defects.

According to him, the depth of the middle portion to be removed is 17 centimetre because the landing is always in the middle, that’s where the aircraft lands.

“That is why we feel that the middle has more structural problem and that is why we are cutting deeper to solve that problem before we put the asphalt.

“The runway was opened in 1982 and no major work has been done on it in almost 35 years after, this is the first major work that is being done on it sine construction.

“It was designed for 20 years and it has been used for additional 15 years so we expect this type of problem,’’ he said.

The Minister of State, Aviation, Sen. Hadi Sirika had on many occasions stated that Abuja airport runway had totally failed due to negligence on the part of the past governments.

This informed the decision of the government to shut the airport for comprehensive repair of the runway and subsequently diverted all Abuja flight to Kaduna airport for six weeks.

NEWSVERGE, published by The Verge Communications is an online community of international news portal and social advocates dedicated to bringing you commentaries, features, news reports from a Nigerian-African perspective. A unique organization, founded in the spirit of Article 19 of the Universal Declaration of Human Rights, comprising of ordinary people with an overriding commitment to seeking the truth and publishing it without fear or favour. The Verge Communications is fully registered with the Corporate Affairs Commission of the Federal Republic of Nigeria as a corporate organization.

Comments
NIGERIA DECIDES

NIGERIA DECIDES

Shell Digital Plan RESPONSIVE600x750
Shell Digital Plan RESPONSIVE600x750
GTB
JoinOurWhatsAppChannel