Connect with us

News

TCN energises 2X60MVA, 132/33KV Gwarinpa Transmission Substation – Official

Published

on

The Transmission Company of Nigeria (TCN) says it has energised the new 2X60 Mega Volt Ampree (MVA) 132/33 (Kilo Volt (KV) Gas Insulated Substation (GIS) at Gwarinpa, Abuja.

Mrs Ndidi Mbah, General Manager, Public Affairs, made this known in a statement in Abuja on Tuesday.

Mbah said that the 132kV substation was one of the five projects comprising the Abuja Ring Projects, funded by Agence Francais de Developpment (AFD).

She said that the substation which had six feeders for bulk electricity transmission to Abuja Electricity Distribution Company’s (AEDCs) load centres, received bulk supply from the Katampe 132kV transmission line.

“With the connection of the substation to the transmission network, TCN has added over 98 megawatts to the national grid.

“The other four substation projects are at various stages of completion. Two will soon be energised while the other two are ongoing.

“Significantly on completion of the entire project, the FCT and environs would have adequate power supply for the next 50years,” she said.

According to her, the Abuja Ring Project is one of the several projects being executed by TCN to further expand the transmission grid.

She said that TCN would not rest on its oars but will continue to work towards further expanding the nation’s grid, to put in place a very robust transmission network.

“That would continue to efficiently transmit bulk electricity to distribution load centres nationwide,” she said.

Constance Athekame

NEWSVERGE, published by The Verge Communications is an online community of international news portal and social advocates dedicated to bringing you commentaries, features, news reports from a Nigerian-African perspective. A unique organization, founded in the spirit of Article 19 of the Universal Declaration of Human Rights, comprising of ordinary people with an overriding commitment to seeking the truth and publishing it without fear or favour. The Verge Communications is fully registered with the Corporate Affairs Commission of the Federal Republic of Nigeria as a corporate organization.

Comments
NIGERIA DECIDES

NIGERIA DECIDES

Shell Digital Plan RESPONSIVE600x750
Shell Digital Plan RESPONSIVE600x750
GTB
JoinOurWhatsAppChannel