The Transmission Company of Nigeria (TCN) has announced the restoration of the Omotosho-Ikeja West Transmission line after it tripped on Wednesday.

Mrs Ndidi Mbah, TCN’s General Manager for Public Affairs, confirmed in a statement on Wednesday that the line had been successfully restored and normal power supply had resumed in the affected areas.

Mbah clarified that at 11:34 p.m. on Wednesday, the Omotosho-Ikeja West 330 Kilo Volt (kV) transmission line tripped at the Omotosho end.

“At the time, the Benin-Egbin 330kV line was undergoing a scheduled outage for mechanical line tracing.

“The tripping caused a cascaded outage, affecting power supply in the Lagos, Abuja, and Osogbo axes.

“However, all other parts of the grid remained unaffected, contrary to media reports of a grid collapse.

“We assure Nigerians of our commitment to efficient delivery of bulk power across the nation as we continue to implement measures to enhance the stability of the national grid,” Mbah said.

Constance Athekame

NEWSVERGE, published by The Verge Communications is an online community of international news portal and social advocates dedicated to bringing you commentaries, features, news reports from a Nigerian-African perspective. A unique organization, founded in the spirit of Article 19 of the Universal Declaration of Human Rights, comprising of ordinary people with an overriding commitment to seeking the truth and publishing it without fear or favour. The Verge Communications is fully registered with the Corporate Affairs Commission of the Federal Republic of Nigeria as a corporate organization.

Comments
NIGERIA DECIDES

NIGERIA DECIDES

Shell Digital Plan RESPONSIVE600x750
Shell Digital Plan RESPONSIVE600x750
GTB
JoinOurWhatsAppChannel